Completed Capital Improvement Projects - 2024-2025

Ballan-Meredith Road - Ballan

Works included pavement widening to achieve a minimum 6.2m seal and the rehabilitation of approximately 3kms of road from 1.6kms north of Lennoxs Lane to 2kms south of Ballan-Egerton Road, minor drainage works, sealing works and linemarking.

Works started: November 2024
Works completed: December 2024

Ballan-Meredith-Road-Moorabuild.jpg

Ballan-Meredith-Road.jpg

Ballan-Meredith-Road-completed.jpg

Ti Tree Road, Dunnstown

Re-sheet and seal existing gravel road shoulder from Old Melbourne Road, Dunnstown to the railway line

Works started: November 2024
Works completed: December 2024

Ti-Tree-Road-Moorabuild.jpg

Ti-Tree-Road-3.jpg

Yendon No 2 Road, Yendon

Road reconstruction from 230m south west of Wiggins Road to Yendon No. 1 Road, including intersection upgrades of Yendon No. 1 Road, Triggs Road, Ramsays Road, Hogarths Road and Wiggins Road.

Works started: October 2024
Works completed: December 2024

Yendon-No.-2.jpg

Yendon-No-2-Road.jpg

Ingliston Road - Ingliston

Works include pavement widening (to achieve 6.2m wide seal) and rehabilitation of approximately 2.6 kilometres, minor drainage works, sealing works, and linemarking. 

Works started: November 2024
Works completed: December 2024

Ingliston-Rd-Construction.jpg

Ingliston-Road.jpg

 

Doyles Road, Elaine

Remove seal and gravel road re-sheet from Midland Highway to Bamganie Road.

Works started: October 2024
Works completed: December 2024

Doyles-Road-Elaine.jpg

 

Old Melbourne Road, Millbrook

Works included widening the road to achieve a 6.2m seal, sealing works, minor drainage works, and linemarking of approximately 1km of road. Location is highlighted below.

Works period: January - February 2025

Old-Melb-Road-Millbrook-map-of-works.png

Old-Melb-Road-Millbrook.jpg