Council offices, including libraries, will be closed from Friday 18 April and will re-open at 8.30am on Tuesday 22 April. Waste collections scheduled for Friday 18 April (Good Friday) will occur the day after on Saturday 19 April. All transfer stations will be closed on Good Friday.For urgent matters, phone 5366 7100 and select the relevant option.
In This Section
Renewal works on the pathways in Maddingley Park are now complete, delivering a key priority project from the Maddingley Park Master Plan. The upgraded concrete paths now connect the main gate to the Station Street exit, and from the lawn tennis courts to the children's playground creating a smoother, more accessible experience for park users. You might notice the edges of the new paths are looking a little bare. Grass seed has been laid and will soon grow to blend beautifully with the surrounding parkland.
The final rehab works on Ingliston Road are now complete. Works included pavement widening and rehabilitation of approximately 2.5kms of road, minor drainage works, sealing works and linemarking. Completion of this section means you can now enjoy a smooth 6.2m wide seal all the way from Ballan to West Maddingley!
Works completed: March 2025
Works included widening the road to achieve a 6.2m seal, sealing works, minor drainage works, and linemarking of approximately 1km of road. Location is highlighted below.
Works period: January - February 2025
Works included pavement widening to achieve a minimum 6.2m seal and the rehabilitation of approximately 3kms of road from 1.6kms north of Lennoxs Lane to 2kms south of Ballan-Egerton Road, minor drainage works, sealing works and linemarking. Works completed: December 2024
Re-sheet and seal existing gravel road shoulder from Old Melbourne Road, Dunnstown to the railway line. Works completed: December 2024
Road reconstruction from 230m south west of Wiggins Road to Yendon No. 1 Road, including intersection upgrades of Yendon No. 1 Road, Triggs Road, Ramsays Road, Hogarths Road and Wiggins Road. Works completed: December 2024
Remove seal and gravel road re-sheet from Midland Highway to Bamganie Road. Works completed: December 2024